吉林Derong - King Blue Bay project
Category:
吉林Housing construction category
Product Description
Building 7#, 9#, 110# in the East Area of Deyong - King Blue Bay Phase I (including pile foundation)
1. Development/construction unit: Langfang Rongxiang Real Estate Development Co., LTD
2. supervision unit: Langfang Tianfeng Project Construction Supervision Co., LTD
3. Design unit: Hebei Tuowei Engineering Design Co., LTD
4. Construction unit: Jiangsu Guangyu Construction Group Co., LTD
5. the construction area of 10,000 square meters/number of layers: 6.67201 CFG pile 1089 ground 26 layers underground 2 layers
6. Structural form: shear wall
7. Contract Date: December 8, 2010 - July 10, 2012
Derong - Dijing 12#-15#, 19# building project
1. Design unit: Hebei Tuowei Engineering Design Co., LTD
2. Construction unit: Yuantong Construction Engineering Group Co., LTD
3. the construction area of 10,000 square meters/number of floors: 8.478604 ground 27 floors underground 2 floors
4. Total investment: 9,8244,103 yuan
5. structural form: shear wall
6. Contract Date: 2012.11.14-2013.12.13
Derong - Dijing 12#-15#, 19# building pile foundation project
1. Design unit: Hebei Yulong Civil Engineering Co., LTD
2. construction unit: Langfang Pengji Construction Foundation Engineering Co., LTD
3. Building scale: Total number of pile foundations: 1347
4. Total investment: 2801,713.89 yuan
5. Contract Date: July 10, 2012 - August 20, 2012